Friday, February 10, 2012

OTN Facilities Delivered; waiting for equipment

The remaining Optical Transport Network (OTN) equipment shelters were delivered this week to Barnum and Floodwood. Equipment for the remodels is still in the process of being ordered or has been ordered. It has been estimated by contractors that it will take 4 to 6 weeks to get all the equipment for the remodel sites. An agreement will need to be approved for the Citon building, which should occur early next week.
The OTN shelters will need to be complete with equipment prior for the network to be operational.